For your information

You are being redirected to one of our divisional subsites which contains more detailed information on the required division. To navigate back to the main Invicta Group site, please click the link found in the footer at the bottom of the page.

Bulkheads & compartments shield Crossrail from fire

Paddington, London

Quick Quote

Contact Fraser Shearer Sarun Vysakham Ben Tan Azim Rizvi Anand Raghavan Our USA Office

Home Case Studies Bulkheads & compartments shield Crossrail from fire

Application

Durasteel Barriers, Bulkheads & Hatches

Fire Rating

2 Hour Integrity, 2 Hour Insulation

Other Performance Criteria

Barrier had a pressure load of 1000 Pa positive pressure

Team Size

4-6 Durasteel Engineers

Company profile

Crossrail is a major railway construction project in London, with work being carried out by the Costain Skanska joint venture. Aiming to provide an entirely new west-to-east passenger rail service, Crossrail will connect two major overground terminuses via a brand new underground line.

Dubbed the Elizabeth Line, it will carry up to 24 trains per hour from near Paddington Station to Stratford, as well as along a new branch from Whitechapel in East London to Abbey Wood in the South East. This is designed to relieve pressure on services in Central London, as well as to improve connectivity for travellers into London from various overground services.

 

Overview

Invicta were approached by WSP & Costain at the early design stage for the fire compartmentation ceilings in riser shafts. This was necessary as the designs had to contend with vertical services passing through the system, with a fire-stopping compound needed to mass-fill the service openings.

There was also a need for M10 and M12 drop rods to be independently fire sealed, as they passed through a number of locations to give support to the passing services.

 

Technical Constraints

Following the successful design of the ceilings in the riser shafts, we were then approached for further design work on bulkhead areas within fire-fighting lobbies, which were needed to protect critical services.

There was also a need for maintenance access through the bulkheads. This required us to draft in an independent structural engineer, who would design a fully insulated access hatch to the same level of protection as the bulkhead.

There were also further protection requirements identified within a stair pressurisation zone. We employed an independent structural engineer to design a barrier which could meet the fire protection requirements, and take into account the performance requirement of +1000Pa pressure load. Due to access only being on one side of the barrier, part of this barrier needed to be constructed in a shaft wall method .

This was compounded by the fact that in some areas, access was only available at night, meaning that we had to work in engineering hours (including dedicated deliveries out of hours). This being a Crossrail project, the sequencing of the installation needed to be diaried and signed off at certain phases of the installation by members of the Crossrail team, further complicating the logistics.

 

Solution

Invicta coordinated designs for all areas which were signed off by all parties. The engineering judgement was carried out for the insulated access hatches required in the bulkhead area. Following design approval, we then coordinated the installation carefully, taking into consideration the requirements of the site and the strict deadlines for certain areas.

 

Benefits

Invicta successfully signed off and issued certification for all systems, on schedule and on budget. Crossrail construction is continuing apace, with the first part of the line expected to open in 2022.

 

Share/Like this page

Accreditations & Affiliations

SpecUp - System Specification Wizard

Answer the 5 short questions below to receive your recommended Durasteel system specifications. Hover over the ? icons for a brief explanation.

Question 1/5

Type of system required?

Question 2/5

Fire rating required?

Question 3/5

Fire integrity-only or integrity and insulation?

Question 4/5

Fire attack risk from one side or both sides of the system?

Question 5/5

Blast rating required in addition to fire rating?

Creating your results page

Thanks for completing the SpecUp, you’ll be redirected to your results shortly.

Click here if you aren't redirected after a few seconds

Start your project

Tell us about your project. Please complete this form. One of our sales team will come back to you with more details. If you prefer, you can drop us an email.





    Project details




    Attach any files that may assist us with your enquiry (specs, drawings, bill of quantities, etc.)

    Acceptable file types are .pdf, .jpg, .dwg, .xls, .xlsx, .doc, .docx, .zip and .rar up to a maximum of 15mb. For files larger than this, please use the external file upload link below.