For your information

You are being redirected to one of our divisional subsites which contains more detailed information on the required division. To navigate back to the main Invicta Group site, please click the link found in the footer at the bottom of the page.

Radiating heat shield protects Dragon LNG from fire

Pembrokeshire

Quick Quote

Contact Fraser Shearer Sarun Vysakham Ben Tan Azim Rizvi Anand Raghavan Our USA Office

Home Case Studies Radiating heat shield protects Dragon LNG from fire

Application

Heat Shield

Fire Rating

4 Hours

Project Timeframe

6 Weeks

Company profile

Dragon LNG is an LNG regasification terminal near the town of Milford Haven in Pembrokeshire, Wales. Together with the nearby South Hook terminal – the largest LNG terminal in Europe – it is capable of handling up to 25% of the UK’s total gas requirement.

Dragon LNG is based on a brownfield site which formerly housed the Gulf oil refinery, which was decommissioned in 1997. As well as connecting to the National Grid plc’s South Wales Gas Pipeline, the LNG terminals also feed the nearby Pembroke B Power Station, the largest gas-fired station in Europe.

 

Dragon heat shieldOverview

Dragon LNG approached us to install a radiating heat shield in a pumphouse at their Milford Haven LNG facility, which first became operational in 2009. The shield would have to provide 4-hour fire integrity as well as protecting nearby personnel and equipment from radiating heat.

The complex nature of the facility would require a bespoke heat shield design, taking into account not only the usual wind load requirements, but also the large deluge pipe system on the building entry line. We were given a six week timeframe for the project, which would cover an area of 451m².

 

Technical constraints

Because we have worked on a number of energy infrastructure projects, we knew our engineers would have to be specially trained for working in a gas facility. Due to the size of the heat shield, the installation would also have to be carried out on specialist fixed scaffolding.

Another aspect of our learning experience on this project was the sensitivity of the surrounding environment. To cater for this, vans would have to be installed with special exhaust systems to prevent combustible fumes from being emitted, allowing them to safely move around the site.

 

Solution

Dragon heat shield

 

As part of our bespoke design process for the heat shield, we ensured that there were openings large enough for the deluge pipework to enter the building area. We also installed vermiculux fire protection boards for the building portal frame, providing heat transfer protection and ensuring that the structure keeps its integrity under intense heat.

Durasteel demountable access panels were used on one elevation for maintenance and inspection use. These allow for demountability by hand as opposed to by using mechanical lifting equipment, expediting the inspection process. We also installed Durasteel doors for personnel access, as well as a separate encasement for a diesel fuel tank used to power the generators.

All four walls (including the roof) were lined with the Durasteel system, so that – in the event of a fire – any heat radiating from the gas tanks would not halt the operation of generators for the deluge systems. As the construction was not down to the floor, there was enough ventilation to prevent the generators from overheating.

 

Result

The project was successfully completed in the six-week period Invicta Durasteel engineers, providing a bespoke demountable panel solution that offered comprehensive heat radiation protection.

The works were successfully installed, signed off and certificated to the highest possible standards, as per the design report and the client’s specifications.

 

Share/Like this page

Accreditations & Affiliations

SpecUp - System Specification Wizard

Answer the 5 short questions below to receive your recommended Durasteel system specifications. Hover over the ? icons for a brief explanation.

Question 1/5

Type of system required?

Question 2/5

Fire rating required?

Question 3/5

Fire integrity-only or integrity and insulation?

Question 4/5

Fire attack risk from one side or both sides of the system?

Question 5/5

Blast rating required in addition to fire rating?

Creating your results page

Thanks for completing the SpecUp, you’ll be redirected to your results shortly.

Click here if you aren't redirected after a few seconds

Start your project

Tell us about your project. Please complete this form. One of our sales team will come back to you with more details. If you prefer, you can drop us an email.





    Project details




    Attach any files that may assist us with your enquiry (specs, drawings, bill of quantities, etc.)

    Acceptable file types are .pdf, .jpg, .dwg, .xls, .xlsx, .doc, .docx, .zip and .rar up to a maximum of 15mb. For files larger than this, please use the external file upload link below.